Hi, all.

I'm having trouble wrapping my head around something and could use your 
help.

I need a new branch.  This project will require : a) purchasing land on 
which to put said branch b) buying a building - I'm wanting a 
metal-framed, modular sort ... NOT a temporary building  c) paying 
professionals to prep the site, construct the building, plumbing, 
electric etc.

My questions:
1) The land purchase would be considered separate from the rest of the 
project in terms of $ amounts and limits for public bid law, right?

2) Since the project IS building a branch, the entire project (b-c 
above) needs to follow RS38:2212 which deals with public work contracts 
rather than 38:2212.1 which deals with purchase of materials and 
supplies ... right?  OR

3) Am I reading RS 38:2218(S) - 
http://www.legis.louisiana.gov/lss/lss.asp?doc=94916 (scroll to the 
bottom)  -  wrong and this is saying that the public works contract 
limit ($150,000 before bid is required) only applies to professional 
fees/wages (c above)  and the supplies(b above) must then follow 
RS38:2212.1?

Getting mixed signals and would appreciate the benefit of your experiences.


-- 
Thank you,